RABIGH II REFINING AND PETROCHEMICAL PROJECT
Project Status: Completed
- Project No : SNA019
- Client : Saudi ARAMCO / SAIPEM
- Location : Rabigh / Saudi Arabia
- Project Start : Sep 2016
- Duration : 6 Ay
- Manpower : 104 People
- Value : 2,786,787.00 $
Miscellaneous excavation, backfilling, reinforced concrete, steel, equipment installation, process piping and instrumentation works.
Scope included 10.000 m3 excavation, 985 m³ concrete, 12 ton chequered plate cover, 12.570 m2 protective coating works.