DUBA DESALINATION PLANT
Project Status: Completed
- Project No : DSD024
- Client : SWCC / Metito Saudi Limited
- Location : Duba / Saudi Arabia
- Project Start : Feb 2019
- Duration : 12 Months
- Manpower : 153 People
- Value : 17,866,666.00 $
Turnkey civil and architectural works for the Duba Water Desalination Plant Project.
Works included Machine Foundations, RO Building, Admin Building, Electrical Building, Intake Electrical Building, Intake Pump Station, Product Water Storage, Neutralization Tank and Guard House, total area of 45,468 m2.
Scope included 17,558 m3 Concrete, 2,016 ton Reinforcing Bar work.